Report: Chatham-Kent Community Hub is on budget and 43% complete

Construction of the new Chatham-Kent Community Hub is on budget and 43 per cent complete, according to a report going to the new council at its first regular meeting on Monday.

“Overall, the project is on budget and is 43 percent complete,” Edward Soldo, the municipality’s general manager of infrastructure and engineering services, wrote in the report.

The hub will combine the Chatham Civic Centre, the Chatham branch of the Chatham-Kent Public Library and the Chatham-Kent Museum in one building at 130 King St. W. Council awarded the construction contract in October 2025. Soldo wrote that the project is being funded through “a combination of property sales, existing reserves, and long-term financing within the Municipality’s existing budget” and will move forward “without any new property tax increases.”

Fortis Construction Group Inc. of Tecumseh is the lead contractor. Work began in December 2025 with site mobilization and demolition of the building’s interior and exterior. Soldo wrote that the north extension, which will house council chambers, and the south extension, which will include a library extension and storage area, are now complete.

“With all structural steel now complete, key milestones have been achieved in roofing, structural steel, building façade and interior works,” he wrote. Mechanical, electrical and fire protection rough-ins continue throughout the building, along with framing, insulation, drywall, stair construction, elevator upgrades and mechanical system installations. Upcoming work will focus on enclosing the exterior before winter and advancing interior rough-ins and fit-outs.

On the budget, Soldo wrote that “The total construction services contract, valued at $39,280,323 (including HST rebate), came in under the previously projected budget.” The initial construction estimate was $42.92 million. The overall project budget remains at $52.8 million, including more than $7 million in contingency funds, which he wrote “aligns with the cost estimate presented to Council in May 2025.”

As of Nov. 4, the report lists the original contract, less HST, at $38,600,945.60 and the revised contract at $38,533,673.49. A total of $16,431,193.93 has been certified over 12 progress payments, with $1,971,743.27 in mandatory holdbacks. The balance remaining is $24,074,222.83. Soldo wrote that the contract has been reduced through seven change orders that provided credits. He also wrote that 43 change orders “to deal with unknown conditions or changes to the design” totalling $1.29 million have been approved against the $3.4-million contingency.

The hub is scheduled to be completed in early 2028. “Detailed transition planning is underway and will be communicated in mid 2027,” Soldo wrote. He wrote that Fortis, the project’s architects, Architectura, and the municipality meet every two weeks and that “There are no known delays to the project schedule.” Updates will be posted on the project’s Let’s Talk page at key milestones.