Agreement signed for North Kent Wind project

North Kent Wind Signing

The agreement was signed on Tuesday for the North Kent Wind project.

This came a day after council gave a vote of confidence towards the two-phase project at their meeting at the Civic Centre on Monday.

“To date, the partnership of Samsung and Pattern has proved to be a very responsible, community-minded corporate citizen,” said Chatham-Kent Mayor Randy Hope. “We have every reason to believe that this new clean energy project will provide substantial revenues to offset taxes while building our economy and our community.”

Council voted in favour of supporting the construction and operation of Phase 1 and Phase 2 of the North Kent Wind Project, a project of Samsung Renewable Energy and Pattern Renewable Holdings Canada ULC.

The project is expected to provide clean renewable energy, substantial tax and permit revenues, and a community benefits fund.

Taking part in Tuesday’s official signing ceremony ( in the photo from left to right), was the Municipality of Chatham-Kent’s Chief Legal Officer John Norton, Entegrus President and CEO Jim Hogan, Mayor Randy Hope, Samsung Vice President of Project Development Jeongtack Lee, Pattern Energy Vice President of Business Development Colin Edwards, North Kent Councillor Leon Leclair, North Kent Councillor Joe Faas, and the municipality’s Chief Administrative Officer Don Shropshire.

Here are some more details about the agreement:

– North Kent 1 will result in approximately $500,000 in building permit fee revenue

– Provides $4 million to the Municipality of Chatham-Kent as a community benefit contribution

– Provides $150,000 for each road remediation project needed

– North Kent 2 Project will result in approximately $500,000 in building permit fee revenue

– Entegrus Transmission Inc. (90% owned by the Municipality of Chatham-Kent) will obtain exclusive maintenance contracts of approximately $300,000 per project per year

– Entegrus can purchase a 15% equity interest in the projects, with North Kent 1 providing the municipality with $4.9 million in dividends, and North Kent 2 providing an additional $2.5 million, all over 20 years

– North Kent 1 & 2 will provide approximately $250,000 per year in property tax revenue

North Kent 1 would place approximately 40 to 50 wind turbines on private lands in both of the former Dover and Chatham Townships.

It is subject to the Province of Ontario’s Renewable Energy Approval process, which requires a detailed and multi-faceted public consultation with municipal government, First Nations, local residents and businesses.

The second project, North Kent 2, depends upon a contract award by the Ontario Independent Electricity System Operator and would place 20 and 40 turbines on private lands in, or near, the former Dover Township. North Kent 1&2 are subject to the provincial permitting and regulatory requirements that regulate industrial wind projects in Ontario.

In 2012 and 2013, Samsung and Pattern completed construction of a 270 megawatt South Kent Wind facility near Blenheim.

They provided $2.5 million for upgrades to the Chatham-Kent Municipal Airport plus community benefits of $11.5 million over the life of the facility.

In addition, the facility will also generate approximately $16 million in property taxes over a 20 year period.