The Otter Creek Wind Farm group is offering up a free water well testing program for concerned residents with active wells near the proposed project infrastructure. Also, consultants hired by Otter Creek say the ‘Golder Report’ issued back in September, applies to their project planned for north of Wallaceburg.
Otter Creek has also submitted its application to the Ministry of the Environment and Climate Change (MOECC) for a Renewable Energy Approval (REA).
Otter Creek officials say as soon as the MOECC confirms the application is complete, in approximately two to three months, there will be a posting on the Environmental Registry whereby the public will be able to comment on the REA submission.
The final REA reports will also be available on the project’s website shortly thereafter.
Free water well testing program
While Otter Creek relies upon the conclusions of qualified experts, it is also committed to being a good neighbour and to helping alleviate the public’s concerns, Otter Creek officials say.
As a result, Otter Creek is also voluntarily committing to testing active water wells within one kilometre of key project infrastructure – specifically wind turbines, the substation and the meteorological tower – prior to starting construction of the facility.
“Tests will be conducted by independent qualified professionals in Ontario and the results of this testing will be given to each landowner that chooses to participate in the program,” Otter Creek officials say.
“During the facility’s construction or within the first year of operation, should any complaints arise from parties that chose to participate in this preconstruction water well testing program, Otter Creek will hire an independent qualified professional to collect a water sample for analysis. Should this analysis confirm there is a water quality issue that was not present in the preconstruction sample, Otter Creek will provide the party with potable water while the complaint is being investigated by a qualified professional (P.Eng. or P.Geo.) hired by Otter Creek to determine whether the change can be reasonably attributed to Otter Creek.”
Complaints arising during the facility’s construction or within the first year of operation from parties within one kilometre of key project infrastructure that did not participate in preconstruction water well testing will be investigated.
However, these parties will not be eligible to receive potable water from Otter Creek during the investigation period, Otter Creek officials stated.
Consultants say ‘Golder Report’ applies
Otter Creek officials say throughout the REA process, several stakeholder groups raised concerns about the construction and operation of wind turbines and their potential impacts on water wells.
“Many of the comments received related to the concern that aquifer-based well water quality would become compromised as a result of vibrations created by pile driving (into the bedrock) during the installation of wind turbine foundations, and/or operation of these turbines with piles,” Otter Creek officials said in a press release.
In response to these concerns, Otter Creek consulted with qualified professionals (licensed P.Eng. and P.Geo.) from both GHD and Golder Associates, two engineering consultant groups, about the potential for pile foundations to have a negative impact on water wells. GHD was hired by Otter Creek to review the report Golder Associates prepared as part of the North Kent Wind 1 Project (the Golder Report, September 2016) to determine whether the conclusions of the report were valid and could apply to the (Otter Creek) project.”
Otter Creek officials say the main conclusions from GHD’s review are:
1. “Based on the similarity of geologic conditions confirmed by GHD at the Otter Creek Site and those presented in the Golder Report, GHD believes that the Golder Report conclusions are applicable to the Otter Creek Site.”
2. “The Report concludes, and GHD concurs, that given that the typical residential well pump operational vibration intensity threshold is in the range of 3 to 9 mm/s, it is highly unlikely (nearly impossible) that vibrations induced by pile driving can cause dislodgement of sediments that would not be otherwise dislodged by existing pump vibration.”
3. “GHD is not aware of any report or study confirming a plausible mechanism for vibrations induced by wind turbine operations to cause sediment dislodgement at distances beyond the common turbine exclusion zones.”
“Based on these conclusions, Otter Creek does not anticipate that either the construction or operation of the facilities will have any negative impact on water wells,” Otter Creek officials stated.
A full copy of Golder’s report can be seen here.
Next steps
The Renewable Energy Approval (REA) application was submitted on March 8.
The public can submit comments directly to the Environmental Registry after MOECC deems that our REA application submission is complete, Otter Creek officials stated.
The public can also continue to communicate with the project team at any time at the contact info below.
The anticipated REA approval date is by late 2017.
The project is a partnership between Renewable Energy Systems Canada (RES), Boralex Inc., as well as Walpole Island First Nation. It would have a capacity up to 50 MW and 12 turbines and includes an investment of $150 million
The project is expectec to be operational by late 2019.
More information is available at www.ottercreekwindfarm.ca