Remediation work continues in Wheatley

Municipal officials say work crews have completed driving a conductor pipe into the bedrock at the APEC 3 site at the northern end of the municipal parking lot in Wheatley.

The 13ā€ pipe surrounds the actual well and material brought to the surface will be used to help determine the nature of the well, Municipal officials added.

Drilling work is finished, and cementing is scheduled for Thursday.

Work has already been completed on APEC 2 (also known as the Tait Well).

Once APEC 3 is completed, remediation will begin on the APEC 1 well, nearest the explosion site.